FDOT OWPB - WP Reports; 5 Year Work Program Item Detail
Office of Work Program and Budget   Julie Adamson - Director
Updated: 2/7/2024 9:33 PM

Five Year Work Program
Selection Criteria
 District 05  2024-2029 G1 
 Orange County  Category:Highways 
 Phase:Construction  Item Number:444315-1 

Display current records in a Report Style
Display current records in an Excel Document

Project Summary
Transportation System:  INTRASTATE INTERSTATE District 05 - Orange County
Description:  SAND LAKE RD INTERCHANGE FROM W OF SR 528 TO W OF SR 435
Type of Work:  INTERCHANGE IMPROVEMENT  View Scheduled Activities
Item Number:  444315-1SIS
Length:  3.449View Map of Item
 
Construction Contract Information
Notice to
Proceed
Date
Work
Begun
Date
Present
Contract
Days
Contract
Days
Used
Percent
Days
Used
02/28/2023 04/03/2023 1411 386 27.36%
Vendor Name: LANE CONSTRUCTION CORPORATION
 
Project Detail
Fiscal Year:202420252026202720282029
Highways/Preliminary Engineering (On-Going)
Amount:  $74,240          
Highways/Railroad & Utilities (On-Going)
Amount:  $542,916          
Highways/Contract Incentives
Amount:  $2,000,000          
Highways/Design Build (On-Going)
Amount:  $4,092,638  $734,706        
 
Item Total: $6,709,794 $734,706